What is the required schedule for inspections?
The following is the required schedule of inspections:
Standing Rule: Before ANY concrete is poured for ANY reason, contact this department for inspection.
- After footings are formed before pouring
- After foundation is formed before pouring
- Before backfilling foundation
- Before basement slab is poured (vapor barrier is required)
- Rough framing and plumbing inspection before insulation is started
- Electrical inspections are handled by third party companies (See below). One of these inspectors must be contacted for any electrical alterations or construction.
- After insulations are complete, before covering
- Final certificate of occupancy/compliance.