What is the required schedule for inspections?

The following is the required schedule of inspections:  
 
Standing Rule: Before ANY concrete is poured for ANY reason, contact this department for inspection.
 
  1. After footings are formed before pouring
  2. After foundation is formed before pouring
  3. Before backfilling foundation
  4. Before basement slab is poured (vapor barrier is required)
  5. Rough framing and plumbing inspection before insulation is started
  6. Electrical inspections are handled by third party companies (See below). One of these inspectors must be contacted for any electrical alterations or construction.
  7. After insulations are complete, before covering
  8. Final certificate of occupancy/compliance.